Services/Features
Sizing & Generator Integration
Power Panel Upgrades
Emergency Systems Routing
Industry Sector
Government
Completion Date
2025
The scope of MEP services for the CFM Generator project at buildings 8, 9, and 31 included a comprehensive electrical upgrade focused on the integration of new generator systems. This involved the design and coordination of new diesel generator system(s), each with automatic transfer switch (ATS), new service entrance conductors, and appropriate grounding systems. Electrical risers and panel schedules were updated to reflect the new generator connectivity and the integration with existing power distribution panels.